Works at new Starbucks drive-thru site are progressing well. We have recently completed both the Foul & Storm water system draiange tie-ins and foundation works. Bulk excavation work to site formations are also complete, with formation of car parking bay and attenuation construction progressing.
The main building works commeneced on programme and 1st fix steel erection is complete, with the sub-structure works now progressing.
Pictured is the steel frame.