Perth High School Earthworks Commenced

Posted on March 16, 2023

Works have commenced to Perth High School Earthworks. A lot of time care and attention has had to go into the forward planning of the earthmoving here due to the current challenging ground conditions and also the inclement weather we will be facing for the 6 week programme.

Kilmac have worked hard to plan out haul routes and bund locations to ensure our tippers can continually run on clean stone throughout to ensure we deliver this 18,000m3 earth moving section of the works on time to allow the follow on works of building footprint piling to commence on target.

Read More: Contract Award

Earthworks Progress
Earthworks Progress
Earthworks Progress