Client: Hall and Partners/Aldi
Commencement Date: March 2022
Main Contract Duration: 9 weeks
Following on from the recent contract award for the new Aldi store in Aberdeen, Kilmac are delighted to be offered the opportunity to continue their relationship with Aldi after successfully securing the groundwork’s package for new RC Ramp, floor areas to rear of store and new Deposit Return Scheme groundworks to front of store.
The award of the groundwork’s package increases the number of projects that Kilmac have undertaken for Hall and Partners/Aldi and the award reinforces the company’s targets to exceed clients’ expectations every time we step onto the park.
Works are due to commence March 2022 with completion date set for end of May 2022.
Works involved from Kilmac are
The project again reaffirms Kilmac ethos to ensure repeat business through client and main contractor satisfaction.