Case Study
Former APS Factory
Client: Dundee City Council
Project Value: £116,000.00
Start Date: 15th May 2017
Contract Duration: 4 weeks
Project Outline
Through competitive tendering via Public Contract Scotland, we are pleased to announce that Dundee City Council have awarded Kilmac the Ground Improvements contract at APS Factory, Pearce Avenue, Dundee.
The works involve the excavation of 4300m³ of unsuitable ground material and subsequent placement of 3000m3 of engineered fill, fully compacted and tested to a regime approved by the Consulting Engineers.
Upon completion of these works the site will be handed back to Dundee City Council to be turned into a staff car park as part of the Tokheim extension project that is currently progressing.