Client: Robertson Construction
Project Value: £300,000
Start Date: May 2016
Contract Duration: 14 months

Project Outline

Construction of a 7 story student accommodation in Aberdeen City Centre. Kilmac’s scope of works include earthworks, foundations, drainage,  attenuation systems, and hard landscaping.

Project Highlights

  • The building footprint covered almost the entire site, therefore programming the construction phasing was key, particular attention was given to the installation sequence of the foundations.
  • Due to the depth of foundations and adjacent ground levels Kilmac had to carry out extensive underpinning and trench fill operations.
  • Due to the lack of a site storage compound, Kilmac had to carefully plan all deliveries taking cognisance of the limited space whilst ensuring the required materials were available for construction.