Usher Institute - Completion of Phase 1

Posted on January 26, 2022

Phase one has now been completed and on programme at the Usher Institute in Edinburgh for main contractor MCLH. Kilmac have completed all major foundations including the lift shaft base, walls and all external main line drainage including the attenuation tank.

The building platform is now ready for the steel erectors (BHC) with crane pads installed and access roads & ramps formed.

This phase went well and has been another good experience working with the main MCLH site team. We look forward to returning for phase 2 in March.