To install a 500kW wind turbine on a shooting estate at Finavon Hill, near Forfar. Kilmac were required to upgrade both public and existing site roads from the A90 to the site, this also included constructing approximately 500 metres of new road. Kilmac also installed 3kms of cable track to allow connection to the national grid. Kilmac acted as main contractor to manage the installation of both SSE, who carried out the electrical connection works and EWT, who installed the wind turbine.
Scope of Works
Bulk excavation, Off site road works, on site roadworks, foundation installation, utility tracking, electrical installation, turbine erection.