Kilmac achieved first milestone on Greenmarket project for Ogilvie
Installation of a 230M3 attenuation tank completed ahead of programme as part of the enabling works at our Greenmarket project with Ogilvie Construction.
Excavation works to remove an existing culvert and infill, along with any rail line remains were carried out. Full excavation for the system was then completed, followed by the installation of a Polystorm attenuation storage tank and associated storm check chamber and hydrobrake.
This will allow us to form the permanent access road and car park for the project and allow full site welfare to be set up for the main construction works.
Well done to all on achieving the first milestone on this project.
Attenuation Tank Install
New Contract Award - Ogilvie Greenmarket
Client: Ogilvie Construction
Commencement Date: April 2022
Main Contract Duration: 9 months
Kilmac are delighted to have been awarded the Groundworks package for the new Office Development in Dundee in partnership with Ogilvie Construction. The new office will be at Greenmarket in the heart of the city centre, close to the waterfront as part of the £1bn regeneration development.
Kilmac works to be undertaken include:
Bulk Earthworks comprising cut/fill operation
Imported stone platforms
Building substructure incorporating Reinforced Concrete
Foundation and Retaining Structures
Waterproofing
Ground Floor Slab
Drainage and Attenuation, within tidal affected water table conditions.
Athole McDonald (Commercial Director):
‘We are delighted to be working with Ogilvie Construction and look forward to commencing on site. Once completed, this development will bring a prominent site back into use and further increase the vibrancy of Dundee City Centre’